Civil Engineering Templates

Contractual Claims (Formulation / Structure)

5/7/2020

1 Comment

 
 Claims structure:
  • Introduction
  • Relevant conditions of contract
  • Chronology of events
  • Cause & effect (impacted programme)
  • Contractors contentions (Heads of Claim)
  • Quantification of time and money
  • Conclusion

Read More
1 Comment

FIDIC 1999 - Dispute process

5/7/2020

1 Comment

 
Clause 20.4 - Obtaining Dispute Adjudication Board’s Decision
“If a dispute (of any kind whatsoever) arises between the Parties in connection with, or arising out of, the contract or the execution of the Works, including any dispute as to any certificate, determination, instruction, opinion or valuation of the Engineer, either Party may refer the dispute in writing to the DAB for its decision, with copies to the other Party and the Engineer. Such reference shall state that it is given under this Sub Clause."

Read More
1 Comment

Concurrency - in Claims / Delays

5/7/2020

0 Comments

 
Concurrency - What does it mean?
Hudson’s Building and Engineering Contracts (10th Edition)., 1 st Supplement - refers to this problem as follows:
“First, different causes of delay may overlap, and this will be intellectually troublesome if one is an event justifying an extension and one not; e.g. information or access may not be available, but due to culpable delay or an event not justifying an extension, the contractor would not have been able to take advantage of them if they had been” (at p. 639)

A concurrent delay is therefore a delay to completion where at least one of the causes of the events which cause delay is at the contractor’s risk. Whereas a parallel delay is a delay to completion involving at least two events neither of which is at the risk of the contractor.

Which creates a bit of a dilemma - Can we agree at the time of a claim event what is the critical path? Especially, if the critical path has changed due to a previous contractor delay, is the employer still culpable for his delay?

Read More
0 Comments

Delay Analysis

5/7/2020

0 Comments

 
Delay & Disruption are measured relative to the Based Line Programme approved by the Engineer or Project Manager.

The process
  • Analyse delays both your own, those that have been caused by the Employer and neutral delays
  • Disruptions slow the progress down
  • Assess these as a Percentage Production Loss over the duration of the activity

Retrospective Delay Analysis (key points)
  • ​Correct Programme logic
  • Reconcile and level critical resources
  • Upgrade from Microsoft Project - you cannot use MSP for a retrospective delay analysis
  • Agree Programme with Engineer (if you can)
  • Impose delays into activities that they affected
  • Identify concurrency
  • Apply “But for” test
  • Identify float usage

Read More
0 Comments

FIDIC 1999 - CLAIM CLAUSES

5/7/2020

0 Comments

 
Clause No: 1.9 - Delayed drawings or Instructions
Event - Late drawing or instruction
Notice - 1.9 Reasonable notice to supply + further 8.4 & 20.1 (28 Days)
Claimable - Cost + Profit
​
Clause No: 2.1 - Right of Access to the Site
Event - Contractor delayed by failure by Employer to give access/possession
Notice - 8.4 & 20.1(28 Days)
Claimable - Cost + Profit

Read More
0 Comments

Monthly Profit / Loss (cost reporting) Concept

7/22/2019

1 Comment

 

Matching concept

The basic and most important Construction tool used to determine Project Profitability is the Cost Reporting process. This guideline will explain the concept of Cost Reporting, understanding the template and the associated software packages. Most software packages today are unable to provide a true cost vs value comparison and thus the need to have a customised Excel template to make the necessary adjustments is extremely important. Most major Contractors today apply this approach. ​

Read More
1 Comment

What is a Geotechnical Report?

4/16/2019

0 Comments

 
A geotechnical report is a tool used to communicate the site conditions and design and construction recommendations for Buildings, structures, roadway or bridge designs, and construction personnel. Site investigations for transportation projects have the objective of providing specific information on subsurface soil, rock, and water conditions. Interpretation of the site investigation information, by a geotechnical engineer, results in design and construction recommendations that should be presented in a project geotechnical report.


Read More
0 Comments

Templates for the Construction Industry

4/15/2019

0 Comments

 
Picture
Let’s face it construction is a risky business. Very few contractors can manage this risk and take their businesses to the next level. It takes great skill / resources / cashflow and quality control to deliver quality projects on time and have all the required paper work in place.

Read More
0 Comments

Eichleay - Head Office Overhead Recovery Method

4/15/2019

1 Comment

 
Picture
When construction is delayed by owner-caused actions, contractors request compensation for the delay. It is difficult to reach agreement on the causes and extent of delay and even tougher to agree on the cost of delay, especially the component costs of home office overhead. This is due, in part, to the lack of a single, accepted method of calculating home office overhead. Here is one acceptable method of calculating Head Office Overhead recovery.

Read More
1 Comment

Document control and stamping

11/24/2015

0 Comments

 
Picture
The importance of this simple yet crucial signature / process marking on documents cannot be more emphasised. Stamping of all business documents according to key processes is essential and have a significance in terms of validity and assurance in information control. The power of these stamps on received or processed documents has been proved time and again and can become key evidence during dispute resolution and law cases. These stamps can either be procured off the shelf from any stationary agency or be specifically designed and company branded at a small cost. Herewith listed some important stamps that is used daily in most businesses.


Read More
0 Comments
<<Previous

    Archives

    May 2020
    July 2019
    April 2019
    November 2015
    October 2015

    Categories

    All
    Contractual
    General
    Planning & Scheduling

    RSS Feed

Support

FAQ
Product Support
​Order Support

Company

About us
Copyright © CivilTemplates.com 2015 - 2023
In partnership with Online-Templatestore.com
All Rights Reserved